Summary
The following article explains how rate tables can be used in Logistics Planning.
More Information
Go to " Logistics Management Job Planning".
- First of all, create a new logistics job.
- Press <F2>. This pulls up the system default rate table.
- If the table shown is not the one you need, press <F5> to move to the "Rate" field.
- Press <F1>/<Shift+F1> to scroll through the tables.
- Press <Enter> when you have found the required table.
- Select the rate you require from the list displayed. Move the cursor to the rate you require and press <Enter>.
- If you are always going to use the same rate, pressing <Alt+F2> from the table will set it as the default rate.