Difference between revisions of "How do I use calculation sequence?"
m |
|||
Line 20: | Line 20: | ||
* You add a [[Hidden Report Generator Columns|hidden]] column 80 that works out the account balance for a date range. | * You add a [[Hidden Report Generator Columns|hidden]] column 80 that works out the account balance for a date range. | ||
* You access this from column 5. | * You access this from column 5. | ||
− | * When column 5 was being added to the report at run time, column 80 wouldn't exist so | + | * When column 5 was being added to the report at run time, column 80 wouldn't exist so its value would be {{DataValue|0}}... |
− | * If you altered the sequence of column 80 to a lower value than column 5, when column 5 was being added to the report, column 80 would exist with | + | * If you altered the sequence of column 80 to a lower value than column 5, when column 5 was being added to the report, column 80 would exist with its value, and that value would be used in column 5.}} |
* Some variables may take a while to evaluate (e.g. Period totals) - these variables hold onto their values until a different period is required, columns that use these should be grouped in sequence. | * Some variables may take a while to evaluate (e.g. Period totals) - these variables hold onto their values until a different period is required, columns that use these should be grouped in sequence. | ||
Line 43: | Line 43: | ||
'''Result''' | '''Result''' | ||
With example 1 the period data is calculated 3 times and for example 2 the period date is calculated 2 times. Depending on the amount of stock history you have this can save massive amounts of time when Platinum is producing the report.}} | With example 1 the period data is calculated 3 times and for example 2 the period date is calculated 2 times. Depending on the amount of stock history you have this can save massive amounts of time when Platinum is producing the report.}} | ||
+ | |||
+ | === Other considerations === | ||
+ | If your report is going to screen or printer, the actual information on the report will be laid out according to the Position field of the columns. If you are sending the information to file, the columns will be laid out according to the {{DataPrompt|Calc. Seq.:}} first and then the position of the column, so your file may not be laid out in the way that you expect. | ||
== See also == | == See also == |
Revision as of 09:18, 28 March 2008
|
This article or section is under review. Be aware: Content may change as the document is reviewed. |
Where
The Calculation Sequence (Known in the Report Generator as "Calc. Seq.:") is used in the "Column Details" section of Report Creation for column types 'Text', 'Numeric' and 'Date'.
Default
Each column is given a Calculation Sequence of '50' as default, allowing other columns to be given lower and higher values to help in the order of their evaluation. Note: only the above column types can have their calculation sequence customised.
Purpose
Each column for the current row will be evaluated in the order dictated by the value entered for the sequence. If columns have the same sequence number, then the column number will be used as the order.
A column with a sequence of '00' will be evaluated before a column with a sequence of '01'. If columns 1 and 2 have a sequence of '50', then column 1 will be evaluated before column 2. If column 1 has a sequence of '51' and column 2 has a sequence of '50' then column 1 will be evaluated after column 2. |
Why go to the Bother?
Seems a lot of bother doesn't it? Why not just keep it set to '50' and forget all about it?
- If you add some columns to an already written report, without the flexibility of this sequence they would always be evaluated after the existing columns. One of these columns may calculate a value that you want to access from an existing column.
|
- Some variables may take a while to evaluate (e.g. Period totals) - these variables hold onto their values until a different period is required, columns that use these should be grouped in sequence.
For the "Stock Control Report Generator" variables 'S14', 'S15', 'S16', 'S17', 'S18', 'S19', 'S20', 'S21', 'S22', 'S23', 'S24', 'S25', 'S65' and 'S66' only re-evaluate if the 'Stock Code' or the 'Period' changes.
Example 1
The above example would evaluate columns 1, 2 and 3 in that order. It would read all the period history for Date Range 1 twice, once for column 1 and again for column 3 (because the Period Range for each column 2 is different). Example 2
The above example would evaluate columns 1, 2 and 3 in the order of 1, 3 and 2. It would read all the period history for Date Range 1 once (because the Period Range for column 3 is the same as column 1). Result With example 1 the period data is calculated 3 times and for example 2 the period date is calculated 2 times. Depending on the amount of stock history you have this can save massive amounts of time when Platinum is producing the report. |
Other considerations
If your report is going to screen or printer, the actual information on the report will be laid out according to the Position field of the columns. If you are sending the information to file, the columns will be laid out according to the "Calc. Seq.:" first and then the position of the column, so your file may not be laid out in the way that you expect.
See also